Investment strategies for mitigation can be scaled only when countries can convert national decarbonisation priorities into implementation-ready projects. Large-scale mitigation does not fail because countries lack ambition, but due to committed finance before the feasibility and implementation readiness are tested. COP31, held in Antalya, Türkiye, focussed on reducing the risk of committing to projects that look viable on paper but cannot be sustained in practice. The central question is no longer how much mitigation finance is mobilised, but whether the countries can convert it into real, measurable, trackable and actionable outcomes.

Developing countries continue to prioritise mitigation finance, but the availability of finance alone will not determine whether mitigation targets are met. India’s net zero pathway illustrates the scale of this challenge. NITI Aayog estimates that India faces a cumulative financing gap of $6.5 trillion by 2070 against the investment need of $22.7 trillion for the net-zero scenario. The power sector accounts for 82 % of this gap, followed by industry and transport. Increased mitigation finance alone will not close India’s net-zero financing gap. It should measure the readiness to build, connect, operate, maintain and finance the asset that delivers the promised emission reductions. Bridging this mitigation finance gap will take unprecedented capital mobilisation across storage and transmission of renewable energy, electric mobility, industrial decarbonization and emerging technologies such as green hydrogen and carbon capture.
Projects stall when investors and funders often mistake a feasibility study for proof that a country can deliver a mitigation asset. For instance, a biogas plant may appear bankable, but weak feedstock supply, offtake arrangements or local technical capacity may fail it. Global Environment Facility (GEF) Project Preparation Grants (PPGs) and Green Climate Fund (GCF) Project Preparation Facility (PPF) are designed to improve the risk-return profile of projects and help countries prepare fundable proposals through funds channelised to assessments on pre-feasibility, technical and scientific design parameters, risk assessment and financial structuring of projects. The feasibility may establish that a technology can work in principle, but they often do not prove whether a country could procure, maintain and keep it operating after warranties expire. A country lacking institutional and technical capacity may get a project approved for paving a pathway to emission reduction and a plausible financial structure. Installed capacity is not delivered mitigation. Hence, treating feasibility as a proxy for implementation readiness only transfer technical and institutional risk from the preparation stage to the implementation stage, where further correcting becomes expensive and disruptive. This emphasizes the importance of preparation support to be redesigned around lifecycle implementation readiness, rather than merely a proposal preparation.
Mitigation projects often require coordination among energy ministries, utilities, regulators, finance ministries, subnational governments, private entities, and local institutions. A solar project may require coordination between a renewable energy developer, a distribution company, a transmission utility and a regulator. The challenge is particularly acute in conflict affected and fragile countries. Evidence from ODI Global (2026) and the Center for Global Development (2026) exposes how countries like Yemen and Somalia with weak data systems, limited institutional capacity, and coordination constraints found it difficult to access readiness and mitigation project pipelines. The central barrier is not simply a lack of data, but the absence of robust climate-aligned project preparation capacity with project preparation units and project development hubs that can facilitate a smoother conversion of national priorities into viable financing pathways. Investment in long-term solutions requires formal mandates, structures and dedicated staffing and resources within countries.
Institutional capacity is the foundation on which technical feasibility, financial sustainability and operations and maintenance performance depend. Funding the feasibility study is not enough within PPF and PPG preparation support. The IMF’s Public Investment Management Assessment (PIMA) provides a useful lens in assessing this gap of whether climate priorities are reflected in national and sectoral plans, and whether the implementing agencies have the capacity to manage procurement, safeguards, monitoring and adaptive management, along with Climate-PIMA (C-PIMA) integrating climate change considerations into public Investment decisions. PIMA treats readiness as a part of the investment cycle and not as an afterthought. A project should not receive full mitigation finance because it has feasibility. The PPG and PPF should be redesigned as implementation-readiness instruments, only then can project implementation deliver sustainable outcomes.

The first reform is to redesign GEF and GCF to support implementation readiness. The support for mitigation projects should move through defined readiness gates, with further finance released only after the technical feasibility, institutional and market readiness, financial and lifecycle operational readiness has been demonstrated. Maintenance records and asset performance data and counting the delivered climate outcome, would help fund projects connected to national priorities. For example, a solar project should require evidence on resource availability, grid integration capacity, curtailment risk, land access, maintenance arrangements and spare-parts supply before full capital finance is released.
Strong domestic institutions reduce dependence on external consultants and make climate finance more responsive to national priorities. Therefore, the second reform could be to build permanent country-level project preparation capacity. For India, this would mean the strengthening of institutional capacity that can prepare, appraise and monitor projects across power, transport, industry, buildings and waste. India already has a strong foundation in climate finance taxonomy, carbon market, green bonds and disclosure frameworks. The next step is to convert this architecture into de-risked and implementation-ready projects.
The third reform may include mapping finance to verified climate outcomes. GEF and GCF should move from financing “climate projects” to implementation-ready mitigation pathways. The Global Infrastructure Hub framework offers a useful model for improvement of mitigation-finance preparation. Every mitigation project should be mapped to a clear transition pathway, sector and asset class, and then assessed against both feasibility and implementation readiness. A project should be identified not simply as “renewable-energy project” but as a solar, wind, storage or transmission asset within a specific mitigation pathway. This allows funders to assess technical risk associated with the asset class and to track whether the project actually delivers emission reductions. Hence, rather than project completion the counting of delivered outcomes would make mitigation finance more credible and effective.
The real test of mitigation is whether a country can operate and maintain the asset. Unless PPFs and PPGs assess implementation readiness as rigorously as they assess the project feasibility, they risk approving projects that look bankable on paper and cannot be delivered or sustained in practice. For India and for other developing countries pursuing net-zero pathways, the effective utilization of mitigation finance should measure the readiness to build, connect, operate, maintain and finance the asset that delivers the promised emission reductions. Closing the implementation readiness gap is not just a technical detail but a bedrock for the transition of climate finance into climate outcomes.